Introduction: What Happened to America’s Next-Generation Frigate?
The Constellation-class frigate was supposed to give the U.S. Navy a modern, affordable warship based on a proven European design. Instead, the program became a cautionary tale about design changes, rising costs, and the challenges of American naval shipbuilding.
On November 25, 2025, the Navy announced a strategic shift away from the program. The agreement with Fincantieri Marinette Marine initially preserved work on the first two frigates, Constellation (FFG-62) and Congress (FFG-63). It terminated the four ships that followed them, FFG-64 through FFG-67. That is a dramatic reversal for a class that, before November 2025, was planned at a total of at least 20 ships.
The numbers explain why. At the time of the decision, Constellation was only about 12 percent complete. Before the restructuring, the Navy projected delivery of the lead frigate in the April 2029 timeframe, roughly 36 months later than the date set in the original contract.
Navy Secretary John Phelan framed the decision in blunt economic terms. In his view, the frigate had reached about 80 percent of the cost of an Arleigh Burke-class destroyer while offering about 60 percent of its capability. That comparison was his justification for the decision, not an official performance metric. Our cost section examines it in context.
The future of the two remaining hulls stayed uncertain through 2026. In February, the Navy moved them from a fixed-price incentive contract to a cost-plus-fixed-fee arrangement, up to the contract’s price ceiling. As of March 2026, the Navy had paused material orders for both ships while they remained under strategic review, and senior Navy officials told GAO the two ships were being reviewed for potential termination.
This guide covers the ship’s design, specifications, weapons, and mission roles, then examines why the program faltered, what it cost, and what comes next.
Constellation-Class Frigate: Quick Facts
- Lead ship: Constellation (FFG-62)
- Shipbuilder: Fincantieri Marinette Marine, Marinette, Wisconsin
- Original program: At least 20 frigates
- Ships under contract before restructuring: Six
- Contracts terminated: FFG-64 through FFG-67
- Remaining ships: FFG-62 and FFG-63, both under review for potential termination
- Design origin: Italian FREMM multi-mission frigate
- Full-load displacement: 7,291 long tons (published design)
- Primary combat system: Aegis Baseline 10
- Primary radar: AN/SPY-6(V)3 Enterprise Air Surveillance Radar (EASR)
- Program status: Further procurement terminated; remaining two hulls under strategic review as reported in 2026
- Planned successor program: FF(X)
1. What Is the Constellation-Class Frigate?
The Constellation class is a multi-mission guided-missile frigate designed to serve as the Navy’s next-generation small surface combatant. It is based on the Italian Navy’s version of the European multipurpose frigate, or FREMM. It follows the troubled Freedom- and Independence-class Littoral Combat Ships, and ongoing difficulties with the LCS were a major factor in the Navy’s original decision to launch the Constellation program.
The competition began with a 2017 request for information. On April 30, 2020, the Navy awarded Fincantieri Marinette Marine a $795.1 million fixed-price incentive contract covering detailed design and construction of the lead frigate, with separately priced options for nine additional ships. That figure is not the total program cost or the final procurement cost of a fully equipped ship. It covers only the shipbuilder’s contract for the lead hull.
The Navy wanted a ship that could destroy surface ships over the horizon, detect enemy submarines, defend convoys, and employ both active and passive electronic warfare systems. In practice, that meant a true blue-water escort, not a lightly armed patrol ship.
The program also carried historic weight. The Navy’s most recent frigate class was the Oliver Hazard Perry (FFG-7) class, with 51 ships procured between FY1973 and FY1984 and decommissioned between 1994 and 2015. At the start of FY2026, the Navy’s small surface combatant force consisted of 32 ships, and none of them were frigates.
2. FFG-62 Specifications and Technical Overview
On paper, the FFG-62 is a large frigate. At over 7,000 tons, it is closer in size to a Cold War-era destroyer than to the Perry-class frigates it was meant to succeed. Much of that growth came from American requirements. The Navy chose to lengthen and widen the hull relative to the FREMM parent design, although officials said the internal layout would largely stay the same.
The CODLAG (combined diesel-electric and gas) propulsion system pairs diesel-generated electrical power with gas-turbine propulsion. Electric drive was intended to reduce machinery-related underwater noise during lower-speed operations, which matters for anti-submarine warfare. The gas turbine provides power for high-speed transits and sprints.
| Specification | Published Design |
|---|---|
| Class | Constellation-class |
| Lead ship | Constellation (FFG-62; not commissioned) |
| Builder | Fincantieri Marinette Marine, Marinette, Wisconsin |
| Length | 496.1 ft (151.2 m) |
| Beam | 64.6 ft (19.7 m) |
| Draft | 18 ft (5.5 m) |
| Full-load displacement | 7,291 long tons |
| Propulsion | CODLAG |
| Main gun | Mk 110 57 mm |
| Vertical launch system | 32 Mk 41 cells |
| Anti-ship missiles | 16 Naval Strike Missiles |
| Point defense | Mk 49 RAM launcher |
| Radar | AN/SPY-6(V)3 Enterprise Air Surveillance Radar (EASR) |
| Combat system | Aegis Baseline 10 |
| Aviation | MH-60R Seahawk helicopter |
Note: This table reflects the published design configuration of the original FFG-62. It is not the verified final fit of a ship in active service.
The Navy’s official fact file lists the class’s length as 496.1 feet, its beam as 64.6 feet, its displacement as 7,291 long tons, and its draft as 18 feet. Its core capabilities include the Enterprise Air Surveillance Radar, the Baseline Ten Aegis Combat System, and the Mk 41 Vertical Launch System, with design flexibility for future growth.
Aegis Baseline 10 and the SPY-6 radar family place the frigate in the same combat system lineage as the Navy’s newest destroyers. That does not make the two ship types equivalent. The FFG-62 carries a smaller three-face radar variant, a 32-cell magazine against the 90 to 96 cells of an Arleigh Burke-class destroyer, and less engineering redundancy. Its design reflects a different mission balance rather than a scaled-down destroyer.
As the following sections show, this high-end ambition was both the program’s greatest strength and one of the reasons it ran into trouble.
3. Weapons and Combat Systems
| Combat System | Planned Capability |
|---|---|
| Aegis Baseline 10 | Integrated combat management |
| AN/SPY-6(V)3 EASR | Air and surface surveillance |
| 32-cell Mk 41 VLS | Naval air-defense missiles |
| 16 Naval Strike Missiles | Over-the-horizon surface strike |
| Mk 110 57 mm gun | Naval gunfire |
| Mk 49 RAM launcher | Point defense |
| AN/SLQ-32(V)6 SEWIP Block II | Electronic warfare support |
| Mk 53 Nulka | Anti-ship missile decoy |
| AN/SLQ-25 Nixie | Towed torpedo countermeasure |
| AN/SQQ-89(V)16 | Undersea warfare integration |
| CAPTAS-4 | Variable-depth sonar |
Note: These systems reflect the published FFG-62 design, not a verified operational configuration.
The FFG-62 was designed as a true multi-mission warship. The Department of Defense’s test and evaluation office lists its intended mission areas as anti-air warfare, anti-submarine warfare, surface warfare, electronic warfare and information operations, and intelligence, surveillance, and reconnaissance. Below is a breakdown of the published combat suite by mission area.
Air Defense: Aegis, SPY-6 and the Mk 41 VLS
The heart of the ship is the Aegis Combat System paired with the AN/SPY-6(V)3 Enterprise Air Surveillance Radar. The AN/SPY-6(V)3 is a three-face, fixed-array radar belonging to the SPY-6 family. Other SPY-6 variants are being integrated into U.S. Navy destroyers and amphibious ships, although their configurations and capabilities differ. Sharing a radar family and combat system lineage can simplify training, software updates, and logistics across the fleet.
The published design incorporated a 32-cell Mk 41 Vertical Launch System intended to accommodate Evolved Sea Sparrow Missiles (ESSM) and selected Standard Missile variants, subject to the ship’s combat-system integration and certification. Physical compatibility with the launcher does not by itself mean a missile is operationally certified on a given ship configuration.
The design also included Cooperative Engagement Capability (CEC), a networked sensor and fire-control system intended to support the exchange of high-quality tracking data among appropriately equipped naval and airborne platforms. In principle, this would allow the frigate to contribute to, and benefit from, a wider fleet air-defense picture.
Surface Warfare: Naval Strike Missile and the 57 mm Gun
For anti-ship strikes, the published design shows 16 Naval Strike Missiles in four quad launchers. These missiles would have provided substantial over-the-horizon anti-ship capability, reinforcing the frigate’s intended role as a more heavily armed and survivable surface combatant than the original Littoral Combat Ship designs.
The Mk 110 57 mm gun was paired with the Advanced Low-Cost Munitions Ordnance (ALaMO) guided projectile and is intended for engaging small boats, drones, and other close-range targets.
Self-Defense and Electronic Warfare
Close-in defense relies on the Mk 49 launcher firing the Rolling Airframe Missile (RAM). Electronic warfare is handled by the AN/SLQ-32(V)6 Surface Electronic Warfare Improvement Program (SEWIP) Block II suite. Beyond detecting and classifying radar emissions, it provides electronic support that feeds threat awareness to the combat system and helps coordinate the ship’s countermeasure responses.
The ship was designed to carry Mk 53 Nulka active decoy launchers, which are intended to lure incoming anti-ship missiles away from the ship. Like any soft-kill countermeasure, a decoy adds a defensive layer but cannot guarantee protection against every threat. The published configuration also included the AN/SLQ-25 Nixie towed torpedo countermeasure system, designed to provide an additional layer of defense against acoustic-homing torpedoes.
FFG-62 Combat System Integration and Operational Risks
Although many individual components were already in service aboard other U.S. Navy platforms, the complete combat-system configuration had not been demonstrated or operationally validated aboard an FFG-62 frigate. The Pentagon’s test office reported in 2023 that the FFG-62 design presented risks to operational effectiveness in each of its primary mission areas: air warfare, anti-submarine warfare, and surface warfare.
The same assessment noted that the ship would rely on unproven system automation and human-system interfaces, and that the Navy acknowledged the risk in its planned crewing strategy. Testers also flagged that the design does not include a tracker illuminator system, which is typically installed on other Aegis platforms. These findings are why this guide describes the frigate’s weapons as published design capabilities rather than proven combat performance.
4. Anti-Submarine Warfare and Operational Roles
Anti-submarine warfare was a central design priority for the Constellation class, reflecting the capabilities and operational emphasis of its FREMM parent design.
Sonar Suite
The undersea warfare system is the AN/SQQ-89(V)16. In FY2022, the Navy modified the design to include the Thales CAPTAS-4, a variable-depth sonar that had not previously been used by U.S. Navy ships. The design also included a multifunction towed array.
Variable-depth sonar allows the sonar array to operate at different depths, helping operators account for changes in underwater sound propagation caused by temperature gradients and other oceanographic conditions. This can improve detection opportunities in environments where hull-mounted sonar performance is limited.
These sensors work best when the ship itself is quiet, which is why the CODLAG electric drive discussed earlier was an important part of the design.
Aviation
The aviation facilities were designed to support an MH-60R Seahawk helicopter and an MQ-8C Fire Scout unmanned aircraft. The MH-60R can employ AGM-114 Hellfire missiles against suitable surface targets and Mk 54 lightweight torpedoes in anti-submarine warfare missions. The actual mix of embarked aircraft would depend on the mission and the Navy’s aviation plans, so it should not be read as a fixed standard deployment.
A shipboard helicopter extends the frigate’s reach well beyond its own sensors: it can deploy sonobuoys, prosecute submarine contacts, and engage surface targets at a distance.
Where a Frigate Fits in the Fleet
The Navy groups frigates with Littoral Combat Ships, mine warfare ships, and patrol craft as small surface combatants. These ships can operate alongside cruisers and destroyers in higher-threat environments or independently in lower-threat areas.
For the FFG-62, the planned roles included escorting convoys and amphibious groups, hunting submarines, and conducting maritime security and presence missions. Taking on those tasks would have freed the Navy’s more expensive Arleigh Burke-class destroyers for high-end air and missile defense.
The frigate was also designed to support the Navy’s distributed maritime operations concept, which calls for spreading combat power across more hulls rather than concentrating it in a few large ships. This was a planned operating concept for the class. No FFG-62 has yet entered service to carry it out.
5. Why Was the Constellation-Class Program Canceled?
Short answer: The Navy halted further Constellation-class procurement in November 2025 after years of design instability, significant weight growth, a roughly three-year schedule slip, and rising costs. The FREMM-based design had diverged so far from its parent that the program lost its promised low-risk advantage, and the Navy turned to a more readily producible alternative.
The FFG-62 program was initially presented as a lower-risk acquisition effort. By adapting a frigate already in service with the Italian and French navies, the Navy expected to avoid the design problems that had plagued earlier shipbuilding programs. That premise did not survive contact with American requirements.
A Parent Design That Stopped Being a Parent Design
According to reporting cited by the Congressional Research Service, design commonality with the original FREMM reportedly declined from approximately 85 percent to less than 15 percent as the Navy incorporated extensive modifications. Changes made to meet U.S. survivability standards and other Navy requirements turned the program into something much closer to a new ship design.
Navy and shipbuilder briefings show the overall length growing from 472.4 feet on the FREMM parent design to 496.1 feet on the FFG-62. That 23.6-foot extension was made to accommodate larger generators and future growth.
The bigger problem was timing. GAO found that the Navy’s decision to begin construction before the design was complete conflicted with leading ship design practices and undermined the low-risk approach. Construction started in August 2022.
Weight Growth and Unreliable Design Metrics
Design changes added weight. Two milestones matter here, and they use different reference points. In October 2023, the shipbuilder reported unplanned weight growth of more than 10 percent above its own June 2020 estimate. By October 2024, the Navy reported 759 metric tons of growth from initial estimates, nearly a 13 percent increase, due in part to underestimating what it would take to apply Navy technical requirements to a foreign design.
Weight growth is not a minor issue for a warship. It erodes the margins needed for future upgrades over a decades-long service life. In April 2024, the Navy said it was considering a reduction in the frigate’s speed requirement as one possible way to resolve the problem. This was an option under evaluation, not an adopted change.
Progress reporting also proved misleading. GAO found that the program’s design stability metric depended largely on the quantity of completed design documents rather than their quality. After the program restructured its metrics, the functional design was reported as 70 percent complete as of December 2024, below the 92 percent reported in August 2023. This did not mean that completed design work had been undone. Rather, the revised assessment exposed how the earlier measurement approach had overstated actual design maturity.
The Final Decision
By the time of the November 2025 decision, the lead ship was about 12 percent complete and years behind schedule. The Navy’s decision reflected a broader reassessment of the program’s affordability, schedule, design maturity, and industrial-base implications. Officials increasingly favored a more readily producible frigate design that could support fleet expansion on a faster timeline.
The four follow-on ships were terminated as part of the Navy’s negotiated restructuring agreement with Fincantieri. The arrangement also addressed existing contractual commitments and measures intended to preserve the shipyard’s workforce and industrial capacity.
Program Timeline at a Glance
| Date | Milestone |
|---|---|
| July 2017 | Navy issues FFG(X) request for information |
| April 30, 2020 | Fincantieri Marinette Marine wins the detail design and construction contract |
| October 2020 | CBO estimates the lead ship could cost about 40% more than the Navy projected |
| August 2022 | Construction begins on FFG-62 |
| April 2024 | Navy discloses an expected delivery delay of about three years |
| May 2024 | GAO reports unstable design and stalled construction |
| October 2024 | Navy reports 759 metric tons of weight growth |
| November 25, 2025 | Navy terminates FFG-64 through FFG-67 |
| December 19, 2025 | Navy announces the FF(X) program and its new design approach based on the National Security Cutter |
| February 2026 | Remaining contract converted to cost-plus-fixed-fee; FY2026 appropriations legislation rescinds frigate funds |
| March 2026 | Material orders for FFG-62 and FFG-63 paused during strategic review |
6. Cost Overruns and Procurement Challenges
How Much Did the Constellation-Class Frigate Cost?
| Comparison (2020 dollars, rounded) | Navy Estimate | CBO Estimate |
|---|---|---|
| Lead ship | ~$1.2 billion | ~$1.6 billion |
| Average per ship, first 10 | $870 million | ~$1.2 billion |
| First 10 ships, total | $8.7 billion | $12.3 billion |
Cost concerns surfaced early. In 2020, the Navy estimated the first 10 frigates would average about $870 million each, or $8.7 billion total, in 2020 dollars. The Congressional Budget Office estimated the lead ship at $1.6 billion and the first 10 ships at an average of about $1.2 billion each, roughly 40 percent above the Navy’s figures.
Budget documents moved in CBO’s direction. Congress provided procurement funding of about $1.3 billion for the first ship in FY2020 and about $1.1 billion for the second in FY2021. These are budgeted procurement amounts, not final ship costs. They also include government-furnished equipment such as combat systems, so they are larger than the shipbuilder’s contract value. GAO later estimated the full 20-ship program at more than $22 billion.
Where the Money Went
Congress appropriated a total of $7.6 billion for the six ships under contract, of which the Navy had spent about $2 billion at the time of the cancellation.
The FY2026 defense appropriations legislation, signed in February 2026, rescinded approximately $2.565 billion in frigate funding. Separately, Congress provided $800 million for the Medium Landing Ship program to help stabilize the affected shipbuilding industrial base, $242 million for long-lead materials for the Navy’s proposed FF(X) frigate, and $100 million for frigate industrial base support and workforce development. A Navy spokesperson said construction funds for FFG-62 and FFG-63 were not affected at the time.
According to GAO’s July 2026 assessment, Navy officials stated that they planned to use approximately $2 billion to secure alternative shipyard workload and support workforce training, development, and retention. This is planned funding, not a completed expenditure.
The February 2026 contract conversion also matters. Under a cost-plus-fixed-fee arrangement, the government generally reimburses allowable incurred costs and pays a predetermined fee, subject to applicable funding limitations and contract terms. This shifts more cost-overrun risk to the government compared with a fixed-price incentive contract.
Putting the “80 Percent Cost, 60 Percent Capability” Claim in Context
Secretary Phelan’s comparison is a useful headline, but not a precise metric. The Navy did not publish the methodology behind it, and the result depends on what is compared: lead ship or follow-on ship, shipbuilder price or total procurement cost, and which destroyer flight serves as the benchmark.
Capability is even harder to reduce to a single number. By magazine size alone, the frigate’s 32 VLS cells equal about one-third of a destroyer’s 96. Yet the FFG-62 incorporated a variable-depth sonar as part of its planned anti-submarine warfare suite, giving it a potentially valuable complementary role alongside destroyers. Neither procurement cost nor combat capability can be meaningfully reduced to a single percentage without defining the comparison criteria and operational scenarios.
The broader point still stands: a frigate meant to be affordable had moved too close to destroyer cost without offering destroyer-level capability.
7. Constellation-Class vs FREMM vs Arleigh Burke: Key Differences
The FFG-62 is often described as a “mini-destroyer” or a “modified FREMM.” Neither label is fully accurate. The table below compares the published FFG-62 design with its European parent and the Navy’s main destroyer.
| Feature | FFG-62 (Published Design) | Italian FREMM (Bergamini Class) | Arleigh Burke Flight IIA/III |
|---|---|---|---|
| Length | 496.1 ft (151.2 m) | ~472.4 ft (144 m) | 509.5 ft (155.3 m) |
| Full-load displacement (metric tonnes) | ~7,408 | ~6,900 | Up to ~9,856 (upper published value) |
| VLS cells | 32 Mk 41 | Sylver launchers; varies by configuration | 96 Mk 41 |
| Primary radar | AN/SPY-6(V)3 | National radars; varies by configuration | SPY-1D(V); SPY-6(V)1 on Flight III |
| Combat system | Aegis Baseline 10 | National systems | Aegis; Baseline 10 on Flight III |
| Primary emphasis | Multi-mission escort, ASW | Multi-mission, strong ASW heritage | Integrated air and missile defense |
| Status | Not commissioned; under review | In service | In service; Flight III in production |
Note: FFG-62 and Arleigh Burke displacements are converted from published long-ton figures to metric tonnes. The Burke value is the upper end of the published range and does not mean all Flight IIA and III ships share the same displacement. FREMM specifications vary by national configuration and source. The comparison uses published Italian FREMM figures and should not be interpreted as representing every French, Italian, or export variant.
FFG-62 vs FREMM: The FFG-62 was meant to be a lightly Americanized FREMM. In practice, it became a longer, heavier ship with U.S. combat systems, U.S. survivability standards, and a substantially different design. The European ship’s operational record does not transfer automatically to the American version.
FFG-62 vs Arleigh Burke: The Arleigh Burke Flight III pairs the larger AN/SPY-6(V)1 radar with Aegis Baseline 10 and retains the 96-cell VLS of earlier destroyers. The frigate shares the Aegis and SPY-6 lineage but carries one-third of the missile cells and a smaller radar variant. Its intended value was in supporting tasks such as escort and anti-submarine warfare, so that destroyers could concentrate on high-end air and missile defense.
8. What Will Replace the Constellation-Class Frigate? FF(X) and Foreign Designs
The Navy’s primary answer is FF(X). Announced on December 19, 2025, the program is based on Huntington Ingalls Industries’ Legend-class National Security Cutter, a frigate-like ship already built for the U.S. Coast Guard.
In April 2026, the Navy awarded HII’s Ingalls Shipbuilding a $282.9 million contract supporting design finalization, long-lead material procurement, and pre-construction activities, with work expected to be complete by April 2028. The broader acquisition strategy envisions expanding production capacity through additional U.S. shipyards.
Specifications revealed in January 2026 describe a ship 421 feet long with a 54-foot beam, a 22-foot draft, a displacement of 4,750 tons, a maximum speed of 28 knots, a 60-day endurance, and a range of 12,000 nautical miles. The Flight I design deviates only slightly from the National Security Cutter in order to speed up production.
The trade-offs are significant. The Navy confirmed that Flight I will not include a built-in Vertical Launch System. Published FF(X) descriptions include a 57 mm main gun, 30 mm secondary armament, a Mk 49 Rolling Airframe Missile launcher, electronic warfare systems, and a flexible aft mission area. The exact final configuration remains subject to design and acquisition decisions.
The aft mission area was designed to accommodate modular payloads, including a proposed 16-missile Naval Strike Missile configuration. Containerized launch systems such as the Mk 70 have also been discussed as potential options, although their integration should not be treated as a confirmed baseline capability.
Development of an improved Flight II began in 2026, and a VLS and anti-submarine warfare equipment are being considered for it. Navy officials have discussed a notional fleet of 50 to 65 FF(X) frigates, although the final procurement quantity remains subject to future force-structure decisions and congressional funding.
Foreign Frigate Designs Under Review
FF(X) may not be the only path. In September 2026, USNI News reported that Japanese, South Korean, and Turkish frigate designs, including the Mogami, Chungnam, and Istanbul classes, were under consideration as part of a parallel U.S. Navy assessment. Navy officials subsequently confirmed that foreign design options were being evaluated alongside the domestic FF(X) program, although no final selection had been announced. Fincantieri has also said it is prepared to build an export FREMM variant in Wisconsin.
As of November 1, 2026, the Navy’s assessment of foreign warship designs was scheduled for submission to the White House by November 12, 2026. Meanwhile, the FF(X) Flight I design has reportedly completed its critical design review, with lead-ship delivery targeted for mid-2030. Completing that review is an important milestone, but it does not eliminate construction or operational testing risks.
9. What the FFG-62 Program Means for U.S. Naval Power
The Constellation program leaves the Navy with a real capability gap. At the beginning of FY2026, the Navy operated 32 small surface combatants, including no frigates. That is approximately 44 percent of the 73-ship objective established in its earlier FY2025 long-range shipbuilding plan. Further delays in fielding replacement frigates could prolong this capability shortfall, depending on future ship deliveries, retirements, and changes to fleet requirements.
The program also leaves clear lessons. First, design maturity has to come before construction. GAO’s central finding was that starting to build an incomplete design undermined the program’s low-risk approach. Second, requirements discipline matters: a parent design only reduces risk if the Navy limits the changes it imposes. Third, shipyard capacity and workforce are strategic assets, not afterthoughts. Congress made this point directly, expecting the Navy to apply lessons from both the Constellation and LCS programs to FF(X).
Finally, FF(X) reflects a different bet. Rather than pursuing another large, highly integrated multi-mission frigate, the Navy is prioritizing production speed, design simplicity, and modular capability growth. The central trade-off is whether faster delivery and greater fleet numbers can compensate for the reduced organic air-defense and anti-submarine warfare capabilities of the initial FF(X) design.
FAQ
Was the Constellation-class frigate canceled?
The Navy terminated contracts for four follow-on frigates in November 2025 and ended plans to continue the original class as envisioned. The two remaining ships, FFG-62 and FFG-63, were subsequently placed under review for potential termination.
Why did the Constellation-class frigate program fail?
The program suffered from extensive design changes to its FREMM-based design, construction that started before the design was mature, significant weight growth, a roughly three-year schedule delay, and rising costs. Together, these undermined the original goal of an affordable, lower-risk frigate.
How many Constellation-class frigates were planned?
The Navy originally planned at least 20 ships. Six were placed under contract between FY2020 and FY2024. Four were terminated in November 2025, leaving two under review.
What weapons and sensors were planned for the FFG-62?
Weapons: a 32-cell Mk 41 VLS, 16 Naval Strike Missiles, a Mk 110 57 mm gun, and a Mk 49 RAM launcher.
Sensors and combat systems: the Aegis Baseline 10 combat system, the AN/SPY-6(V)3 radar, the AN/SQQ-89(V)16 undersea warfare system, and a CAPTAS-4 variable-depth sonar.
Aviation: an MH-60R Seahawk helicopter.
What is replacing the Constellation-class frigate?
The Navy’s primary replacement program is FF(X), based on the Coast Guard’s Legend-class National Security Cutter and led by HII’s Ingalls Shipbuilding. It is not the only option under study: the Navy is also evaluating foreign frigate designs, and no final decision on that track had been announced as of November 2026.
Is Constellation (FFG-62) operational?
No. The ship has not been delivered or commissioned. It was about 12 percent complete in November 2025 and remains under strategic review.
What is the difference between the FREMM and the Constellation class?
The Constellation class started from the FREMM design but was lengthened, made heavier, and fitted with U.S. combat systems and survivability features. According to news reporting cited by the Congressional Research Service, design commonality fell from about 85 percent to less than 15 percent.
How much does a Constellation-class frigate cost?
Congress provided about $1.3 billion in procurement funding for the first ship and about $1.1 billion for the second. These are budgeted amounts, not final costs. CBO estimated in 2020 that the lead ship could cost about $1.6 billion. No final ship cost exists because no ship has been completed.